Gary Grossman, Assistant Transportation Engineer
This project, which will construct a four-lane roadway from SR 776 to CR 775 (near Buck Creek), will complete the missing link of the proposed hurricane evacuation route from CR 775 to River Road in Sarasota County.
Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.
| Project Task |
Start |
Finish |
Complete |
Contractor |
|---|---|---|---|---|
| Design | 6/14/04 |
3/31/09 | 100% | Wilbur Smith |
| Permitting | 09/25/09 | 09/25/09 | 90% | |
| Right-of-Way | 1/26/09 | 8/3/09 | 90% | |
| Construction | On Hold |
Comments:
Per Board action, construction is on hold.