Project Status Update

Oyster Creek Clearing

John DeGiovine, Project Manager

This project provides for the removal of nuisance and exotic vegetation from Oyster Creek and the Gondolier Waterway to help enhance the flow of stormwater through the creek.  This will help drain the Englewood East area and the Oyster Creek Subdivision quickly, in the event of a major storm.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Construction 01/19/09
10/30/09
78%  
Checklist Process
01/19/09 01/19/09
100%
 
Documents to Purchasing
01/22/09 01/22/09
100%
 
Pre-Bid Scheduled
03/24/09 03/24/09 100%  
Bid Opening
05/06/09 05/06/09 100%  
Administrative Approval 05/26/09 05/26/09 100%  
Pre-Construction Meeting 06/03/09 06/03/09 100%  
Notice to Proceed
06/22/09 06/22/09 100%  
Construction
06/22/09
10/19/09
78%  
Clearing Oyster Creek 06/22/09
10/19/09
100%  
Optional Clearing Early WW 08/24/09 10/19/09 33%  
Certification Received 10/26/09 10/26/09 100%  
Final Invoice from Contractor 10/27/09 10/27/09 0%  
Close Project 10/30/09 10/30/09 0%