Project Status Update

Northwest Port Charlotte Bridge Rehabilitation

CIP Project C410515

Chuck Koons, Project Engineer

This project provided for renovation of the Eisenhower Drive Bridge over the Cheshire Waterway and the Jacobs Street Bridge over the Jupiter Waterway.

Project Task
Start Date
Finish Date
% Complete
Contractor
Design 09/01/05 09/29/08
100%
 
Bid Opening 10/01/08 10/01/08 100%  
Notice to Proceed 01/05/09 01/05/09 100%  
Construct Eisenhower Bridge 01/26/09 04/30/09 100% American Earth Movers
Close Roadway to Traffic 01/26/09 01/26/09 100%  
Demolition 01/26/09 02/06/09 100%  
Form/Pour Deck 02/09/09 03/06/09 100%  
Form/Pour East Approach Slab 03/11/09 03/13/09 100%  
Form/Pour West Approach Slab 03/11/09 03/13/09 100%  
Form/Pour Barrier Wall 03/16/09 03/18/09 100%  
Form/Pour Sidewalk 03/18/09 03/20/09 100%  
Install Railing
03/27/09
03/27/09
100%  
Substantial Completion
03/27/09
03/27/09
100%  
Punch List
03/27/09
04/30/09
100%  
Bridge Complete 04/30/09 04/30/09 100%  
Construct Jacobs Bridge 04/13/09 06/09/09 100% American Earth Movers
Close Roadway to Traffic 04/13/09 04/13/09 100%  
Demolition 04/13/09 04/24/09 100%  
Form/Pour Deck 04/27/09 05/11/09 100%  
Form/Pour North Approach Slab 05/12/09 05/14/09 100%  
Form/Pour South Approach Slab 05/12/09 05/14/09 100%  
Form/Pour Barrier Wall 05/21/09 05/25/09 100%  
Form/Pour Sidewalk 05/15/09 05/18/09 100%  
Install Railing 05/22/09 05/26/09 100%  
Install Guardrail 05/27/09 05/28/09 100%  
Substantial Completion 06/03/09 06/03/09 100%  
Punch List 06/04/09 06/09/09 100%  
Bridge Complete 06/09/09 06/09/09 100%  
Substantial Completion 06/10/09 07/28/09 100%  
As-Builts Received 06/10/09 08/18/09 100%  
Submit As-Builts 08/19/09 08/27/09 100%  
Final Invoice 08/28/09 09/07/09 100%  
Close Project 09/08/09
09/08/09
100%