Project Status Update

Northwest Charlotte Maintenance Dredge

CIP Project C390403

Chuck Mopps, Project Manager

The purpose of this project is to facilitate safe navigation within the waterway system by removing approximately 7,100 cubic yards of silted material and placing it on upland sites.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Mobilize on Site 12/01/08 12/04/08 100% Millmac Corporation
Dredging
12/05/08
09/24/09
71%
 
Exterior Venus Waterway 12/05/08 06/08/09 100%  
Interior Cheshire Waterway 12/18/08 09/24/09 81%  
Interior Venus Waterway 02/20/09 03/06/09 99%  
Exterior Cheshire Waterway 03/03/09 06/03/09 100%  
Interior Markham Waterway 03/10/09 09/24/09 80%  
Exterior Apollo Waterway 05/04/09 06/16/09 100%  
Interior Apollo Waterway 05/15/09 08/31/09 82%  
Ingersol Waterway 06/11/09 09/21/09 0%  
Bayview Waterway 07/17/09 09/14/09 0%