Project Status Update
Midway Boulevard Water Control Structures Phase 1
John DeGiovine, Project Manager
This project is being completed in conjunction with Phase 1 of the Midway Boulevard Widening Project. Affected structures include the locations where the following waterways intersect Midway Boulevard: Elkcam Waterway, Yale Waterway, and Niagara Waterway.
Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.
| Project Task |
Start Date |
Finish Date |
% Complete |
Contractor |
|---|---|---|---|---|
| Construction | 09/01/09 | 05/15/11 | 2% | |
Documents to Purchasing |
09/01/09 | 09/01/09 | 100% |
|
Pre-Bid Meeting |
09/15/09 | 09/15/09 | 100% | |
Bid Opening |
10/07/09 | 10/12/09 | 100% | |
| Goldenrod Preparation | 10/12/09 | 10/16/09 | 100% | |
BCC Approval |
10/27/09 | 10/27/09 | 0% | |
Pre-Construction Meeting |
11/04/09 | 11/04/09 | 0% | |
| Respond to RFI's | 11/05/09 | 11/11/09 | 0% | |
| Construction | 11/05/09 | 02/12/11 | 0% | |
| Substantial Completion | 02/13/11 | 02/13/11 | 0% | |
| As-Built Survey | 02/14/11 | 03/15/11 | 0% | |
| Punchlist Items | 02/14/11 | 02/27/11 | 0% | |
| Project Certification (Submit As-Builts) | 03/16/11 | 05/14/11 | 0% | |
| Close Project | 05/15/11 | 05/15/11 | 0% |