Public Works
Project Status Update
Fordham Waterway Bridges at US 41 Service Roads
This project provides for the replacement of the Fordham Waterway bridge structures at both the US 41 South Access Road and US 41 North Access Road. These bridges were constructed in 1958 and 1963 and are functionally obsolete. The new structures will accommodate the proposed beautification and pedestrian facilities planned for the US 41 corridor, with their widths increased to allow for sidewalks.
Future dates and durations associated/ with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.
| Project Task |
Start Date |
Finish Date |
% Complete |
Contractor |
|---|---|---|---|---|
| Utility Design | 02/03/06 |
05/24/07 |
100% |
|
| Construction | 05/25/07 |
10/22/08 |
100% |
Engineering Control Systems |
Checklist Process |
05/25/07 |
06/07/07 |
100% |
|
Bid Documents to Purchasing |
06/07/07 |
06/07/07 |
100% |
|
Drawings/Advertising to Purchasing |
06/08/07 |
07/19/07 |
100% |
|
Pre-Bid Scheduled |
07/19/07 |
07/19/07 |
100% |
|
Bid Opening |
08/15/07 |
08/15/07 |
100% |
|
Goldenrod Preparation |
09/24/07 |
10/08/07 |
100% |
|
BCC Approval |
10/09/07 |
10/09/07 |
100% |
|
Pre-Construction Meeting |
10/29/07 |
10/29/07 |
100% |
|
Notice to Proceed |
12/03/07 |
12/03/07 |
100% |
|
Construction |
12/04/07 |
10/22/08 |
100% |
|
| Project Close-Out | 10/23/08 | 11/27/09 | 86% | |
Punchlist Items |
11/12/08 | 07/21/09 | 100% | |
As-Builts Received |
03/18/09 | 11/06/09 | 85% |
|
| Submit As-Builts | 11/06/09 | 11/17/09 | 0% | |
Final Invoice |
11/17/09 | 11/26/09 | 0% |
|
Close Project |
11/26/09 | 11/27/09 | 0% |