This project provides for the replacement of the Fordham Waterway bridge structures at both the US 41 South Access Road and US 41 North Access Road.  These bridges were constructed in 1958 and 1963 and are functionally obsolete.  The new structures will accommodate the proposed beautification and pedestrian facilities planned for the US 41 corridor, with their widths increased to allow for sidewalks.

Future dates and durations associated/ with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Utility Design
02/03/06
05/24/07
100%
 
Construction
05/25/07
10/22/08
100%
Engineering Control Systems
Checklist Process
05/25/07
06/07/07
100%
 
Bid Documents to Purchasing
06/07/07
06/07/07
100%
 
Drawings/Advertising to Purchasing
06/08/07
07/19/07
100%
 
Pre-Bid Scheduled
07/19/07
07/19/07
100%
 
Bid Opening
08/15/07
08/15/07
100%
 
Goldenrod Preparation
09/24/07
10/08/07
100%
 
BCC Approval
10/09/07
10/09/07
100%
 
Pre-Construction Meeting
10/29/07
10/29/07
100%
 
Notice to Proceed
12/03/07
12/03/07
100%
 
Construction
12/04/07
10/22/08
100%
 
Project Close-Out 10/23/08 11/27/09 86%  
Punchlist Items
11/12/08 07/21/09 100%  
As-Builts Received
03/18/09 11/06/09
85%
 
Submit As-Builts 11/06/09 11/17/09 0%  
Final Invoice
11/17/09 11/26/09
0%
 
Close Project
11/26/09 11/27/09
0%