Public Works
Project Status Update
Coral Creek Bridge Replacement
This project will replace the existing bridge on CR 771 over Coral Creek in Placida. The new structure will enhance recreational access by increasing the span between the bridge supports and adding about one foot of additional clearance for boaters. The project will also eliminate the sharp curve at the junction of CR 775 and CR 771.
Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.
| Project Task |
Start Date |
Finish Date |
% Complete |
Contractor |
|---|---|---|---|---|
| Design | 04/01/02 |
03/25/09 |
100% |
Keith and Schnars |
Initial Design |
04/01/02 |
12/26/05 |
100% |
|
Utility Relocation Design |
06/16/06 |
11/30/07 |
100% |
|
Permit Modifications |
12/03/07 |
08/27/08 |
100% |
|
100% Plan Review |
08/28/08 |
09/10/08 |
100% |
|
Design Corrections |
09/11/08 |
03/25/09 |
100% | |
Plans Complete |
03/25/09 | 03/25/09 | 100% |
|
| Permitting | 03/03/03 |
11/07/08 |
100% |
|
Southwest Florida Water Management District |
03/03/03 |
09/15/05 |
100% |
|
Florida Department of Environmental Protection |
03/03/03 |
12/26/05 |
100% |
|
US Fish & Wildlife Service |
03/03/03 |
09/15/05 |
100% |
|
Florida Fish & Wildlife Conservation |
03/03/03 |
09/15/05 |
100% |
|
Purchase of Mitigation Credits |
03/01/06 |
08/29/06 |
100% |
|
Archeological Survey |
03/01/06 |
05/09/07 |
100% |
|
Submerged Lands Easement |
03/01/06 |
09/26/06 |
100% |
|
SHPO Review |
05/10/07 |
10/24/07 |
100% |
|
Addended Report to SHPO |
11/27/07 |
11/07/08 |
100% |
|
US Coast Guard |
08/15/03 |
01/02/08 |
100% |
|
USACOE |
07/11/07 |
12/21/07 |
100% |
|
| Construction | 02/04/08 |
10/15/10 |
65% |
|
Checklist Process |
02/04/08 |
03/12/08 |
100% |
|
Documents to Purchasing |
03/12/08 |
04/18/08 |
100% |
|
Pre-Bid Meeting |
04/18/08 |
04/18/08 |
100% |
|
Bid Opening |
04/18/08 |
06/25/08 |
100% |
|
Goldenrod Preparation |
06/25/08 |
07/09/08 |
100% |
|
BCC Approval |
07/22/08 |
07/22/08 |
100% |
|
Pre-Construction Meeting |
07/22/08 |
08/06/08 |
100% |
|
Procurement |
08/06/08 |
09/29/08 |
100% |
|
Ground Breaking |
09/29/08 |
09/29/08 |
100% |
|
Notice to Proceed |
09/29/08 |
09/29/08 |
100% |
|
Construction |
09/29/08 |
10/15/10 |
55% |
|
| Project Close-Out | 10/15/10 | 07/15/11 | 0% | |
Substantial Completion |
10/15/10 |
12/17/10 |
0% |
|
Punchlist Items |
12/17/10 |
01/28/11 |
0% |
|
As-Builts Received |
01/28/11 |
04/22/11 |
0% |
|
Submit As-Builts |
04/22/11 |
06/03/11 |
0% |
|
Final Invoice |
06/03/11 |
07/15/11 |
0% |
|
Close Project |
07/15/11 |
07/15/11 |
0% |