| Project Task |
Start Date |
Finish Date |
% Complete |
Contractor |
|---|---|---|---|---|
| Construction | 08/12/09 | 03/16/10 |
2% | |
Checklist Process |
08/12/09 | 08/12/09 | 100% |
|
Documents to Purchasing |
09/29/09 | 09/29/09 | 100% |
|
Pre-Bid Scheduled |
11/25/09 | 12/29/09 | 0% | |
Bid Opening |
12/30/09 | 12/30/09 | 0% | |
| Goldenrod Preparation | 12/31/09 | 12/31/09 | 0% | |
| BCC Approval | 01/01/10 | 01/01/10 | 0% | |
| Pre-Construction Meeting | 01/04/10 | 01/04/10 | 0% | |
Notice to Proceed |
01/05/10 | 01/05/10 | 0% | |
Construction |
01/06/10 | 03/09/10 |
0% | |
| Substantial Completion/Rating | 03/10/10 | 03/10/10 |
0% | |
| Punchlist Items | 03/11/10 | 03/11/10 | 0% | |
| As-Builts Received | 03/12/10 | 03/12/10 | 0% | |
| Submit As-Builts | 03/15/10 | 03/15/10 | 0% | |
| Final Invoice | 03/16/10 | 03/16/10 | 0% |