Project Status Update

Cape Haze Drive Bridge Replacement

CIP Project C410603

Chuck Koons, Project Engineer

This project provides for replacement of the Cape Haze Drive Bridge, which provides a critical transportation link for West County residents. The Bridge, which spans the Amberjack Cove Waterway, is located on Cape Haze Drive, approximately .15 miles east of CR 775. 

The existing structure does not conform to current standards for lane width, and the existing deck and abutments need to be repaired. The cost of these repairs make it more effective to replace the structure. Funding will be provided by the Placida Street and Drainage MSBU.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Design Procurement
01/02/06
08/14/06
100%
 
Prepare RFP for Purchasing
01/02/06
03/22/06
100%
 
RFP to Purchasing
03/23/06
04/12/06
100%
 
Pre-Submittal Meeting
05/02/06
05/02/06
100%
 
RFP Due
05/16/06
05/16/06
100%
 
RFP Scored
06/09/06
06/09/06
100%
 
Recommendation Goldenrod to BCC
06/09/06
06/09/06
100%
 
Designer Selected
06/27/06
06/27/06
100%
 
Scope of Services Meeting
07/20/06
07/20/06
100%
 
Develop Scope of Services
07/20/06
08/07/06
100%
 
Designer Contracted
08/14/06
08/14/06
100%
 
Total Project
08/14/06
06/02/09
100%
 
Notice to Proceed
08/14/06
08/14/06
100%
 
Topographic and ROW Survey
08/14/06
09/15/06
100%
 
Geotechnical Investigation
08/14/06
09/01/06
100%
 
Conceptual Design
09/04/06
03/15/07
100%
 
Develop Conceptual Report
09/04/06
10/06/06
100%
 
Internal QC of Conceptual Report
10/09/06
10/13/06
100%
 
Incorporate Internal QC Comments
10/16/06
10/17/06
100%
 
Submit Conceptual Report
10/17/06
10/17/06
100%
 
County Review
10/18/06
01/09/07
100%
 
Revise Conceptual Report
01/10/07
03/07/07
100%
 
County Review
03/08/07
03/15/07
100%
 
County Approval
03/15/07
03/15/07
100%
 
Submit Preliminary Plans to Utilities
03/07/07
03/07/07
100%
 
90% Plans
03/08/07
06/02/09
100%
 
Final Structural Design
03/08/07
04/11/07
100%
 
Final Roadway Analysis
03/08/07
03/28/07
100%
 
Utility Design
03/29/07
04/18/07
100%
 
Develop Final Structural Plans
03/22/07
05/02/07
100%
 
Develop Final Roadway Plans
03/22/07
05/02/07
100%
 
Compute Quantities
05/03/07
05/09/07
100%
 
Internal QC of 90% Submittal
05/10/07
05/16/07
100%
 
Incorporate Internal QC Comments
05/17/07
05/23/07
100%
 
Submit 90% Plans
05/23/07
05/23/07
100%
 
County Review
05/24/07
04/10/09
100%
 
Accepted for Economic Stimulus Funding 04/07/09 04/07/09
100%
 
Submit 90% Comments
04/10/09 04/10/09
100%
 
Incorporate County Comments
04/13/09 05/27/09
100%
 
Bid Documents to FDOT 05/28/09 06/02/09
100%
 
100% Plans
06/02/09 06/02/09
100%
 
Permitting
05/24/07
04/07/08
100%
 
SWFWMD
10/15/07
02/15/08
100%
 
Coast Guard
05/24/07
12/10/07
100%
 
USACOE
12/04/07
04/07/08
100%
 
Construction Procurement
07/01/09
11/30/09
70%
 
Economic Stimulus Funding in Place
07/01/09
07/01/09
100%
 
FDOT Lets Project
07/01/09
09/30/09
100%
 
Bids Due
09/30/09
09/30/09
100%
 
Contract Awarded
10/01/09
11/30/09
25%
 
Pre-Construction Meeting
11/30/09
11/30/09
0%
 
Notice to Proceed
11/30/09
11/30/09
0%
 
Construction
12/01/09
08/16/10
0%
 
Mobilization/Construction
12/01/09
07/12/10
0%
 
Substantial Completion
07/12/10
07/12/10
0%
 
Punch List
07/13/10
08/16/10
0%
 
Substantial Completion
08/17/10
09/06/10
0%
 
As-Builts Received
09/07/10
09/27/10
0%
 
Project Complete
09/27/10
09/27/10
0%