Replacement of this structure is part of the overall plan to improve the drainage flow through the canal system, up to the 100-year storm event. The design of this structure is consistent with Master Stormwater Management Plan requirements. The work is located at Sunset Waterway and Peachland Boulevard.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Request for Design Proposal
10/22/07
01/09/08
100%
 
Request to Purchasing
10/22/07
10/22/07
100%
 
Proposal Received
10/23/07
10/23/07
100%
 
Consultant Selection
11/07/07
11/07/07
100%
 
Scope of Services
12/07/07
12/12/07
100%
 
Review/Approve/Reject
12/13/07
12/13/07
100%
 
Notice to Proceed
12/20/07
12/20/07
100%
 
Signed Contract Received
01/09/08
01/09/08
100%
 
Design
11/08/07
10/31/08
100%
 
Survey
11/08/07
01/10/08
100%
 
30% Plan Review
02/27/08
03/14/08
100%
 
60% Plan Review
04/18/08
05/14/08
100%
 
90% Plan Review
08/27/08
10/31/08
100%
 
100% Plan Review
08/27/08
10/31/08
100%
 
Permitting
06/23/08
09/23/08
100%
 
Construction 11/12/08 01/02/10 90%  
Checklist Process 11/12/08 11/27/08 100%  
Documents to Purchasing 01/29/09 01/29/09 100%  
Pre-Bid Scheduled 04/08/09 04/08/09
100%
 
Bid Opening 04/29/09 04/29/09
100%
 
Goldenrod Preparation 04/30/09 04/30/09
100%
 
BCC Approval 05/26/09 05/26/09
100%
 
Pre-Construction Meeting 06/09/09 06/09/09
100%
 
Notice to Proceed 07/26/09 07/26/09
100%
 
Construction 07/26/09 12/18/09
99%
RS Construction
Substantial Completion 12/19/09 12/19/09
0%
 
Punchlist Items 12/20/09 12/29/09
0%
 
As-Builts Received 12/30/09 12/30/09
0%
 
Submit As-Builts 12/31/09 12/31/09
0%
 
Final Invoice 01/01/10 01/01/10
0%
 
Close Project 01/02/10 01/02/10
0%