Project Status Update
Lionheart Water Control Structure
John DeGiovine, Project Manager
The design of this structure is consistent with Master Stormwater Management Plan requirements. Replacement of this structure is part of the overall plan to improve the drainage flow through the canal system, up to the 100-year storm event. The work is located at Lionheart Waterway and Forrest Nelson Boulevard, at Mile Post 2.87.
Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.
Project Task |
Start Date |
Finish Date |
% Complete |
Contractor |
|---|---|---|---|---|
| Request for Design Proposal | 10/22/07 |
01/18/08 |
100% |
|
Request to Purchasing |
10/22/07 |
10/22/07 |
100% |
|
Proposal Received |
10/23/07 |
10/23/07 |
100% |
|
Consultant Selection |
12/13/07 |
01/18/08 |
100% |
|
Scope of Services |
12/20/07 |
12/20/07 |
100% |
|
Approve/Reject |
12/20/07 |
12/20/07 |
100% |
|
Notice to Proceed |
12/20/07 |
12/20/07 |
100% |
|
Signed Contract |
01/01/08 |
01/11/08 |
100% |
|
| Design | 12/07/07 |
10/31/08 |
100% |
|
Survey |
12/07/07 |
02/15/08 |
100% |
|
30% Plan Review |
03/07/08 |
03/28/08 |
100% |
|
60% Plan Review |
04/18/08 |
05/14/08 |
100% |
|
90% Plan Review |
08/27/08 |
10/31/08 |
100% |
|
100% Plan Review |
08/27/08 |
10/31/08 |
100% |
|
| Permitting | 06/23/08 |
09/23/08 |
100% |
|
| Construction | 11/12/08 | 05/12/10 | 18% | |
Checklist Process |
11/12/08 |
11/18/08 | 100% | |
Documents to Purchasing |
01/29/09 | 01/29/09 | 100% |
|
Pre-Bid Date Scheduled |
04/08/09 | 04/08/09 | 100% | |
Bid Opening |
04/29/09 | 04/29/09 | 100% |
|
Goldenrod Preparation |
04/30/09 | 04/30/09 | 100% |
|
BCC Approval |
05/26/09 | 05/26/09 | 100% |
|
Pre-Construction Meeting |
06/09/09 | 06/09/09 | 100% |
|
Notice to Proceed |
07/26/09 | 07/26/09 | 100% |
|
Construction |
11/23/09 | 04/21/10 | 12% |
RS Construction |
Substantial Completion/Rating |
04/22/10 | 04/22/10 | 0% |
|
Punchlist Items |
04/23/10 | 05/06/10 | 0% |
|
As-Builts Received |
05/07/10 | 05/07/10 | 0% |
|
Submit As-Builts |
05/10/10 | 05/10/10 | 0% |
|
Final Invoice |
05/11/10 | 05/11/10 | 0% |
|
Close Project |
05/12/10 | 05/12/10 | 0% |