CAPITAL IMPROVEMENT PROJECTS
Jail Expansion - The jail expansion will double the current 528 inmate housing, and add four out buildings: training armory, video visitation, Sheriff Maintenance, and work release. The project consists of two phases. The first phase will include the project site work and construction of the out buildings, and the second phase is to expand and renovate portions of the existing jail. Construction on the out buildings started on May, 2007. The project is estimated to be complete by January of 2009. The budget amount is $44,871,000.